This project required that the complete refurbishment and M&E installation work was completed in separate phases over three floors while maintaining the client's business on site at all times; having worked with the THWG team before I knew that I would be able to count on their professionalism and commitment... Both the client and I were not disappointed; the finished project has been completed to a high standard and within the required time constraints.

Design Director, A C Liani (Yorkshire) Limited

Investec Wealth & Investment

10th July 2012

Project Value: £900k

Duration: 32 weeks (phased)

"

The team have a great attitude and are there to solve problems, not create them. I've been impressed by the quality of their building and joinery work and by their commitment to deliver a great end result for the client. They take time to understand exactly what is required whilst maintaining a sense of urgency.

Director of Design

The Blue Boar Hotel

27th March 2012

Project Value: £1.4 million

Duration: 18 weeks

"

THWG demonstrated an extraordinary ability to deal with and actively solve problems on site.

Client

Zizzi Harrogate

2013

Project Value: £397,000

Duration: 12 weeks